Drainage pipe replacement at Bay Area & Choate Road

No Picture

Dear EHCMA Member:

As per the email below the contractor will be mobilizing this Friday, June 7th to the location below to start work Monday, June 10, to start replacing some drain pipe that crosses the road on Bay Area BLVD. just north of Choate Road.  The contractor will open and close lanes as needed, the job will take roughly 9 to 10 days, barring any weather issues.  

Here is the following information concerning the upcoming construction repair for the pipe replacement at Bay Area Blvd & Choate Road:

Start Date: Monday, June 10, 2019

End Date: Wednesday, June 19, 2019

Hours of Operations: 7:00 am – 5:30 pm

Project Scope: Remove and replace the existing pavement and drainage pipe at Bay Area Blvd and Choate Road.

Traffic Control Plan: One lane will be closed at a time during the pavement removal and pipe replacement (The traffic control plan is attached)

Any questions or concerns, please let me know. Also, if we have any changes in the schedule I will let you know immediately.

TCP-LL TCP-RL

Respectfully,

Sent by Pamela Parker, EHCMA, on behalf of:

Arcadio Avalos Jr.

Road and Bridge Operations